DEFINITIONS
DPR:
ENGINEER OF RECORD / DESIGN
PROFESSIONAL OF RECORD.
SPECIAL
INSPECTOR:
A QUALIFIED PERSON, APPROVED BY THE DPR WHO HAS
DEMONSTRATED COMPETENCE TO THE SATISFACTION OF THE BUILDING OFFICIAL AND
THE DPR FOR INSPECTION OF THE PARTICULAR TYPE OF CONSTRUCTION OR
OPERATION REQUIRING SPECIAL INSPECTION. DUTIES INCLUDE VISUAL
INSPECTIONS AND FIELD MEASUREMENTS OF MATERIALS, OBTAINING SPECIMENS FOR
TESTING AND RELATED ACTIONS INCLUDING PREPARATION OF REPORTS. (REF
1701.2 & 1701.3)
TESTING
LABORATORY:
A QUALIFIED MATERIALS TESTING LABORATORY UNDER THE
RESPONSIBLE CHARGE OF A LICENSED PROFESSIONAL ENGINEER, APPROVED BY THE
BUILDING OFFICIAL AND THE DPR, TO MEASURE, EXAMINE, TEST, CALIBRATE OR
OTHERWISE DETERMINE THE CHARACTERISTICS OR PERFORMANCE OF CONSTRUCTION
MATERIALS AND VERIFY CONFIRMATION WITH CONSTRUCTION DOCUMENTS.
CONTINUOUS
INSPECTION:
INSPECTION BY THE SPECIAL INSPECTOR CONTINUOUSLY
OBSERVING ALL WORK REQUIRING SPECIAL INSPECTION. (REF 1701.6.1).
PERIODIC
SPECIAL INSPECTION:
INTERMITTENT
INSPECTION PERFORMED AS OUTLINED IN THE PROJECT PLANS AND
SPECIFICATIONS, AND APPROVED BY THE BUILDING OFFICIAL (REF 1701.6.2).
STRUCTURAL
OBSERVATION:
VISUAL OBSERVATION OF THE STRUCTURAL
SYSTEM, BY THE DPR OR DESIGNEE, INCLUDING BUT NOT LIMITED TO THE
ELEMENTS AND CONNECTIONS, FOR GENERAL CONFORMANCE TO THE APPROVED PLANS
AND SPECIFICATIONS, AT SIGNIFICANT CONSTRUCTION STAGES AND AT COMPLETION
OF THE STRUCTURAL SYSTEM. STRUCTURAL OBSERVATION DOES NOT INCLUDE OR
WAIVE THE RESPONSIBILITY FOR THE SPECIAL AND MUNICIPAL INSPECTIONS
REQUIRED BY CODES AND SPECIFICATIONS. (REF 220 & 1702).
APPROVED
FABRICATOR:
A FABRICATOR QUALIFIED BY AN ACCREDITED BODY APPROVED BY
THE BUILDING OFFICIAL AND DPR, TO PERFORM WORK OFF SITE, WITHOUT SPECIAL
INSPECTION. (REF 1701.7).
1.0
GENERAL INFORMATION
THE DESIGN PROFESSIONAL OF RECORD (DPR) SHALL SUBMIT AN
INSPECTION PROGRAM TO THE BUILDING OFFICIAL FOR APPROVAL PRIOR TO
ISSUANCE OF THE BUILDING PERMIT. THE PROGRAM SHALL IDENTIFY THE PORTION
OF THE WORK THAT REQUIRES SPECIAL INSPECTION / STRUCTURAL OBSERVATION
AND DESCRIBE THE DUTIES OF THE SPECIAL INSPECTOR AND THE STRUCTURAL
OBSERVER (REF 106.3.5).
1.02 THE
OWNER OR ITS DESIGNEE SHALL EMPLOY THE SPECIAL INSPECTOR OR INSPECTION
AGENCY
TO PERFORM INSPECTIONS
SPECIFIED IN THIS SECTION. (REF 1701.1).
1.03 THE
OWNER OR ITS DESIGNEE SHALL EMPLOY THE MATERIAL TESTING LABORATORY TO
PERFORM TESTS
SPECIFIED IN THIS SECTION.
1.04 ACCREDITATION
TO ASTM E-329-2000, (OR LATER VERSION) STANDARD SPECIFICATIONS FOR
AGENCIES
ENGAGED IN THE INSPECTION AND THE
TESTING OF MATERIALS USED IN CONSTRUCTION, IS PREFERRED.
THE OWNER OR ITS DESIGNEE SHALL EMPLOY THE DESIGN PROFESSIONAL
RESPONSIBLE FOR THE STRUCTURAL
DESIGN OR ANOTHER ENGINEER OR ARCHITECT
DESIGNATED BY THE DPR TO PERFORM STRUCTURAL OBSERVATION.
(REF 1702).
HIGH
STRENGTH BOLTING
HIGH
STRENGTH BOLTING SHALL BE INSTALLED IN
ACCORDANCE WITH THE “SPECIFICATIONS FOR STRUCTURAL JOINTS USING ASTM
A325 OR A490 BOLTS” AS APPROVED BY THE RESEARCH COUNCIL ON STRUCTURAL
CONNECTIONS OF THE ENGINEERING FOUNDATION, UNLESS OTHERWISE NOTED ON THE
APPROVED PLANS AND SPECIFICATIONS.
A. WHILE
THE WORK IS IN PROGRESS, THE SPECIAL INSPECTOR SHALL DETERMINE THAT THE
REQUIREMENTS OF 3.9.1 FOR BOLTS, NUTS, WASHERS AND PAINT; BOLTED PARTS,
INSTALLATION AND TIGHTENING STANDARDS ARE MET.
B. THE
SPECIAL INSPECTOR SHALL OBSERVE THE CALIBRATION PROCEDURES WHEN SUCH
PROCEDURES ARE REQUIRED BY THE PLANS AND SPECIFICATIONS, AND SHALL
MONITOR THE INSTALLATION OF BOLTS TO DETERMINE THAT ALL PLIES OF
CONNECTED MATERIALS HAVE BEEN DRAWN TOGETHER AND THAT THE SELECTED
PROCEDURE IS PROPERLY USED TO TIGHTEN ALL BOLTS.
C. FOR
ALL BOLTED CONNECTIONS THAT ARE SPECIFIED TO BE SLIP CRITICAL OR SUBJECT
TO AXIAL TENSION, THE SPECIAL INSPECTOR SHALL VERIFY THAT THE SPECIFIED
PROCEDURES WERE FOLLOWED TO ACHIEVE THE PRETENSION SPECIFIED.
D. BOLTS
IN CONNECTION, IDENTIFIED AS NOT BEING SLIP-CRITICAL NOR SUBJECT TO
DIRECT TENSION NEED NOT BE INSPECTED FOR BOLT TENSION OTHER THAN TO
ENSURE THAT THE PLIES OF THE CONNECTED ELEMENTS HAVE BEEN BROUGHT INTO
SNUG CONTACT.
E. PERIODIC
INSPECTION FOR BOLTED CONNECTIONS MAY BE PERFORMED IN ACCORDANCE WITH
THE REQUIREMENTS OF SECTION 1701.6.2 OF THE UBC, OR AS DEFINED ON 3.9.1.
|
WORK REQUIRING
SPECIAL INSPECTION AND STRUCTURAL OBSERVATION DURING:
(TO BE SELECTED
AND CHECKED BY THE DESIGN PROFESSIONAL OF RECORD) |
SPECIAL INSPECTION |
STRUCT
OBSERV |
|
CONTINUOUS |
PERIODIC |
|
BOLTING |
A |
HIGH STRENGTH
BOLTING. |
|
|
|
|
|
|
|
|
|
INSPECTION REPORTS
THE SPECIAL INSPECTOR SHALL SUBMIT
INSPECTION AND TESTING REPORTS TO THE DPR, THE BUILDING OFFICIAL, THE
CONTRACTOR, THE OWNER AND OTHER DESIGNATED PERSONS AT A REASONABLE
FREQUENCY, AS ESTABLISHED IN THE PRE-CONSTRUCTION MEETING.
THE SPECIAL INSPECTOR SHALL SUBMIT A FINAL
REPORT STATING WHETHER THE WORK REQUIRING SPECIAL INSPECTION WAS IN
CONFORMANCE TO THE APPROVED PLANS AND SPECIFICATIONS AND THE APPLICABLE
PROVISIONS OF THE CODE.
SPECIAL INSPECTION REPORTS SHALL INCLUDE,
BUT NOT LIMITED TO THE FOLLOWING:
A.
PROJECT ADDRESS.
B. PERMIT
NUMBER AND GOVERNMENT AGENCY HAVING JURISDICTION.
C. NAME
AND ADDRESS (PHONE AND E-MAIL) OF DPR.
D. OWNER’S
AGENT RELEVANT TO THE WORK.
E. DATE
OF INSPECTION AND HOURS WORKED.
F.
DESCRIPTION OF INSPECTIONS PERFORMED,
INCLUDING LOCATION (REFERENCE GRID LINES AND FLOORS OR
ELEVATION).
G. STATEMENT
THAT WORK INSPECTED CONFORMS TO APPROVED PLANS AND SPECIFICATIONS.
H.
LIST OF UNRESOLVED DEVIATIONS, EXCLUSIONS
AND/OR ADDITIONS TO APPROVED PLANS AND SPECIFICATIONS
AUTHORIZED BY DPR.
I. CORRECTIONS
OF PREVIOUSLY LISTED ITEMS WITH REFERENCE TO ORIGINAL REPORT INDICATING
REJECTION.
J. LIST
OF TEST SPECIMENS TAKEN; MILL CERTIFICATIONS RECEIVED; NOTICE OF
COMPLIANCE OR NON-COMPLIANCE
ISSUED; CONCRETE MIX DESIGNS USED; WPS AND IDENTIFICATION
NUMBERS; NAMES OF QUALIFIED PERSONNEL
SUCH AS WELDERS AND PNEUMATIC CONCRETE OPERATORS.
K. NAME,
IDENTIFICATION NUMBER AND SIGNATURE OF INSPECTOR PERFORMING THE SPECIAL
INSPECTION.
L. CORRECTION REPORTING REQUIREMENTS
ALL DISCREPANCIES SHALL BE BROUGHT TO THE IMMEDIATE ATTENTION OF
THE CONTRACTOR FOR CORRECTION,
THEN, IF UNCORRECTED WITHIN 24 HOURS, TO THE DPR AND TO THE
BUILDING OFFICIAL.
MATERIAL TESTING CRITERIA AND REPORT
DEVELOPMENT
THE NUMBER AND FREQUENCY OF TAKING OF TEST
SPECIMENS AND TESTING SHALL BE THE MINIMUM REQUIRED BY THE GOVERNING
CODES, STANDARDS, OR AS SPECIFIED IN THE APPROVED PLANS, WHICHEVER IS
MORE STRINGENT.
LABORATORY TEST RESULTS AND/OR MILL
(SUPPLIER) CERTIFICATIONS SHALL BE SUBMITTED TO THE CONTRACTOR, DPR AND
THE BUILDING OFFICIAL TO INCLUDE, BUT NOT BE LIMITED TO THE FOLLOWING:
A.
CONCRETE MIX DESIGNS.
B.
REINFORCING STEEL AND PRESTRESSING
TENDONS.
C.
CONCRETE TEST SPECIMENS.
D.
STRUCTURAL STEEL MEMBERS AND WELD
MATERIALS.
E.
SHEAR CONNECTORS AND HIGH STRENGTH BOLTS.
F. MASONRY
UNITS.
G.
SPECIMENS OF MORTAR, GROUT AND PRISMS.
H.
SHOT CRETE SPECIMENS.
I. WELD
QUALIFICATION TESTS.
J. NON-DESTRUCTIVE
TESTING.
K.
TORQUE TESTS.
L.
PULL TESTS
QUALITY ASSURANCE
·
GENERAL
INFORMATION
·
DEFINITIONS
·
STRUCTURAL OBSERVATION
·
SPECIAL
INSPECTION AND MATERIAL TESTING
·
INSPECTION REPORTS
·
MATERIAL
TESTING CRITERIA AND REPORT DEVELOPMENT
·
REINFORCED CONCRETE
·
STRUCTURAL MASONRY
·
STRUCTURAL STEEL WELDING
·
HIGH
STRENGTH BOLTING
.
SUMMARY OF INSPECTION / OBSERVATION REQUIREMENTS
REINFORCED
CONCRETE
CONTINUOUS
INSPECTION IS REQUIRED:
A.
DURING THE PLACEMENT OF
REINFORCEMENT AND CONCRETE IN MOMENT-FRAMES RESISTING DESIGN SEISMIC
LOAD IN STRUCTURES WITHIN
SEISMIC ZONES 3 & 4. (EXCEPTIONS SECTION 1701.5.1 AND 1701.5.4 OF THE
CODE.)
B.
DURING THE MOULDING OR
CONSTRUCTION OF CONCRETE CYLINDERS, BEAMS, CORES OR PANELS.
C.
DURING PLACEMENT OF
REINFORCING STEEL AND CONCRETE FOR DRILLED PILES OR CAISSONS.
D.
DURING THE STRESSING AND
GROUTING OF TENDONS IN PRESTRESSED CONCRETE PER DESIGNATED SEQUENCE.
E.
PRIOR TO AND DURING THE
PLACEMENT OF CONCRETE AROUND ANCHOR BOLTS WHEN APPLICABLE, PER SECTION
1923 OF THE UBC, AND TABLE 19-D NOTE 5.
F.
PRIOR TO AND DURING THE
INSTALLATION OF ADHESIVE / GROUTED ANCHORS.
G.
DURING THE PLACEMENT OF
SHOTCRETE AND TAKING OF TEST SPECIMENS AS REQUIRED BY SECTIONS
1701.5.12,
1924.10 AND 1924.11.
PERIODIC INSPECTION IS REQUIRED:
A. AT
THE START AND DURING EACH PHASE OF THE PROJECT TO ASCERTAIN PROPOSED
CONFORMITY
OF MATERIALS, PERSONNEL
QUALIFICATIONS AS REQUIRED, AND PROCEDURES WITH THE APPLICABLE
CODES, PLANS AND SPECIFICATIONS.
B.
REINFORCEMENT AND TENDON
PROFILE VERIFICATION PRIOR TO CLOSING OF FORMS OR THE DELIVERY OF
CONCRETE TO THE JOBSITE.
C.
DURING THE PLACEMENT OF
CONCRETE (ONLY WHERE PERMITTED BY CODE)
D. AT
SUCH FREQUENCY AS NECESSARY TO CLEARLY CONFIRM THE PLACEMENT OF TIES,
HOOPS, STIRRUPS,
CONNECTIONS, AND ANY ADDITIONAL SPECIFIED
REINFORCEMENT (I.E. AT OPENINGS, BEAMS,
CORNERS, COLUMNS, PIERS AND CAISSONS)
BEFORE THEY ARE COVERED.
E. DURING
SAMPLING OF CONCRETE AT DISCHARGE FROM MIXER.
F. FOR
VERIFICATION OF DELIVERED MIX DESIGN BEFORE ANY CONCRETE IS PLACED.
|
WORK REQUIRING
SPECIAL INSPECTION AND STRUCTURAL OBSERVATION DURING:
(TO BE SELECTED
AND CHECKED BY THE DESIGN PROFESSIONAL OF RECORD) |
SPECIAL INSPECTION |
STRUCT
OBSERV |
|
CONTINUOUS |
PERIODIC |
|
CONCRETE |
A
CONCRETE PLACEMENT.
1.
FOUNDATION/FOOTINGS.
2.
SLAB-ON-GRADE.
3.
ALL OTHER STRUCTURAL
CONCRETE. |
|
|
|
|
B |
PLACEMENT OF NON
SHRINK GROUT |
|
|
|
|
C |
MOLDING OF
COMPRESSION TEST SAMPLES. |
|
|
|
|
D |
PLACEMENT OF
REINFORCEMENT AND CONCRETE IN CAISSONS. |
|
|
|
|
E |
PLACEMENT OF
CONCRETE AROUND BOLTS OR EMBEDS AS SPECIFIED (REF. 1701.5 #2). |
|
|
|
|
F |
PNEUMATICALLY
PLACED CONCRETE, PERSONNEL QUALIFICATION, REBAR PLACEMENT
CONDITIONS, SAMPLE PANEL VERIFICATION. |
|
|
|
|
G |
PLACEMENT OF HIGH
STRENGTH GROUT AND TAKING SAMPLES |
|
|
|
|
H |
CONCRETE BATCHING
ON-SITE. |
|
|
|
|
I. |
WEIGHT MASTER
CERTIFICATION. |
|
|
|
|
|
|
|
|
|
|
DRILLED ANCHORS |
A |
INSTALLATION OF
ADHESIVE ANCHORS, RODS AND DOWELS. |
|
|
|
|
B |
EXPANSION ANCHORS
IN CONCRETE OR MASONRY. |
|
|
|
|
REINFORCING STEEL |
A |
PLACEMENT OF
REINFORCING BARS. |
|
|
|
|
B |
SAMPLING FOR
TESTING. |
|
|
|
|
C |
MILL REPORT
VERIFICATION AND MATERIAL IDENTIFICATION. |
|
|
|
|
D |
PRESTRESS TENDON
PROFILE, VERIFY EQUIPMENT CALIBRATION, OBSERVE AND RECORD ELONGATION
& FORCE. |
|
|
|
|
|
|
|
|
|
SPECIAL INSPECTION AND MATERIAL TESTING
CONSTRUCTION SCHEDULE
THE CONTRACTOR SHALL BE RESPONSIBLE FOR
PROVIDING THE SPECIAL INSPECTOR AND/OR TESTING LABORATORY WITH A
CONSTRUCTION SCHEDULE AND SAFE ACCESS FOR PERFORMING INSPECTION /
ON-SITE TESTING.
THE SPECIAL INSPECTOR
THE FOLLOWING SHALL PROVIDE THE SPECIAL
INSPECTION DUTIES:
|
|
|
SPECIAL INSPECTOR OR FIRM
|
|
ADDRESS
|
|
CONTACT NAME AND PHONE NUMBER (S) |
ALTERNATE INSPECTORS OR FIRMS ARE
ALLOWED, WITH PRIOR WRITTEN APPROVAL BY THE BUILDING OFFICIAL AND THE
DPR.
MATERIAL
TESTING
MATERIAL
TESTING SHALL BE PERFORMED BY A TESTING LABORATORY, APPROVED BY THE
BUILDING OFFICIAL AND THE
DPR.
|
|
|
TESTING LABORATORY
|
|
ADDRESS
|
|
CONTACT NAME AND PHONE NUMBER (S) |
ALTERNATE TESTING LABORATORIES ARE
ALLOWED, WITH PRIOR, WRITTEN APPROVAL BY THE BUILDING OFFICIAL AND
DPR.
STRUCTURAL MASONRY
CONTINUOUS INSPECTION
AS REQUIRED BY SECTION 1701.5.7:
A.
DURING PREPARATION AND
TAKING OF PRISMS OR TEST SPECIMENS.
B.
DURING PLACEMENT OF
ALL MASONRY UNITS AND REINFORCEMENT.
C.
VERIFICATION OF CLEAR
GROUT SPACES AND IMMEDIATELY PRIOR TO CLOSING CLEANOUTS.
D.
DURING ALL GROUTING
OPERATIONS.
PERIODIC INSPECTION IS REQUIRED:
A. AT
THE START AND DURING EACH PHASE OF THE PROJECT TO CONFIRM MATERIAL
CERTIFICATIONS AND TESTING
REQUIREMENTS, PERSONNEL QUALIFICATIONS AS
REQUIRED, AND PROCEDURES WITH THE APPLICABLE CODES,
PLANS AND SPECIFICATIONS.
B. AT
SUCH FREQUENCY AS NECESSARY, TO VERIFY THAT THE CLEANLINESS, MORTAR
PROJECTIONS AND
REINFORCEMENT CLEARANCES WITHIN GROUT
SPACES, CONFORM TO MINIMUM REQUIREMENTS.
C. TO
VERIFY THAT THE GROUT POURS AND CONSTRUCTION JOINTS ARE IN COMPLIANCE
WITH SECTION 2104.6.1 OF
THE UBC.
D. CHECK
TO VERIFY THAT ALL DOWELS, ANCHOR BOLTS AND INSERTS ARE SECURED IN PLACE.
|
WORK REQUIRING
SPECIAL INSPECTION AND STRUCTURAL OBSERVATION DURING:
(TO BE SELECTED
AND CHECKED BY THE DESIGN PROFESSIONAL OF RECORD) |
SPECIAL INSPECTION |
STRUCT
OBSERV |
|
CONTINUOUS |
PERIODIC |
|
MASONRY |
A |
PLACEMENT OF
MASONRY UNITS. |
|
|
|
|
B |
MASONRY PRISM
CONSTRUCTION, MORTAR AND GROUT SAMPLING. |
|
|
|
|
C |
GROUTING
OPERATIONS. |
|
|
|
|
D |
MATERIALS
CERTIFICATION. |
|
|
|
|
E |
MASONARY WALLS
COMPLETION. |
|
|
|
|
|
|
|
|
|
STRUCTURAL
OBSERVATION
THE CONTRACTOR SHALL BE RESPONSIBLE FOR
NOTIFYING THE DPR 48 HOURS IN ADVANCE OF REQUIRED
OBSERVATION (S) FOR SCHEDULING PURPOSES. FAILURE BY THE CONTRACTOR TO
MEET OBSERVATION SCHEDULES MAY REQUIRE REMOVAL OF ANY SUBSEQUENT WORK
FOR OBSERVATION. REMOVAL AND REPLACEMENT OF ANY FINISHED WORK AND/OR
FRAMING DAMAGED BY THE REMOVAL PROCESS OR AS REQUIRED FOR CORRECTIVE
ACTION SHALL BE AT THE CONTRACTOR’S EXPENSE. APPROVAL BY THE MUNICIPAL
INSPECTOR DOES NOT REPLACE OBSERVATION BY THE DPR. APPROVAL BY THE DPR
DOES NOT REPLACE THE INSPECTION PROCESS BY THE MUNICIPAL INSPECTOR AND
ANY OTHER INSPECTION REQUIREMENTS.
A PRE-CONSTRUCTION MEETING SHALL BE HELD
TO REVIEW THE SCHEDULE AND DETAILS OF THE STRUCTURAL SYSTEM TO BE
OBSERVED, TO VERIFY THE CONTRACTOR’S UNDERSTANDING OF THE PLANS,
SPECIFICATIONS, TESTS AND INSPECTIONS AND REVIEW CRITICAL CONSTRUCTION
DETAILS. THE MEETING SHALL INCLUDE THE DPR AND THE PARTY RESPONSIBLE
FOR THE STRUCTURAL OBSERVATION, THE CONTRACTOR, SPECIAL INSPECTOR, AND
SUBCONTRACTORS.
THE STRUCTURAL OBSERVER SHALL, AS A
MINIMUM, PERFORM STRUCTURAL OBSERVATIONS AT THE FOLLOWING STAGES OF
CONSTRUCTION:
A. CONCRETE
AND REINFORCING STEEL: AFTER EXCAVATION OR FORMING AND PLACEMENT OF
REINFORCING
STEEL, PRIOR TO CONCRETE PLACEMENT
AND CLOSING OF FORMS.
B.
STEEL FRAMING: AFTER STEEL ERECTION,
PRIOR TO DECKING AND PLACEMENT OF CONCRETE OR FIREPROOFING.
C.
UPON COMPLETION OF SHEAR WALL (S) AND/OR
THE ANCHORAGE SYSTEM.
D.
BEFORE INSTALLATION OF FINISH MATERIA |